Skip to main content

Manage high availability

Beta

As of June 15, Lakebase is available in Beta on GCP. See Region availability for supported regions.

This guide covers enabling and managing high availability for your Lakebase endpoints. For background on how high availability works and how secondary compute instances differ from standalone read replicas, see High availability.

Enable high availability​

To enable high availability, set the compute type and HA configuration in the UI or configure the endpoint's EndpointGroupSpec via the API.

Prerequisites​

  • Scale to zero must be disabled. In the UI, set Scale to zero to Off in the edit compute drawer. Via the API, set no_suspension: true in the endpoint spec (use spec.suspension as the update mask).

After creating a project, click the primary compute link from the project dashboard to open the edit compute drawer.

Project dashboard showing the production branch with its primary compute link

Set Compute type to High availability, then choose a Configuration under High availability:

  • 2 (1 primary, 1 secondary),
  • 3 (1 primary, 2 secondaries),
  • or 4 (1 primary, 3 secondaries) total compute instances.

Edit compute drawer showing the Compute type toggle set to High availability and the Configuration dropdown with options for 2, 3, or 4 total compute instances

Lakebase provisions secondary compute instances in different availability zones. Once all compute instances are active, the endpoint has automatic failover.

Configure read-only access to secondary compute instances​

Allow access to read-only compute instances controls whether secondary compute instances serve read traffic via the -ro connection string.

  1. On the Computes tab, click Edit on the primary compute.
  2. Under High availability, check or uncheck Allow access to read-only compute instances.
  3. Click Save.
warning

With only one secondary compute instance and read access enabled, all read traffic on the -ro connection string is interrupted during a failover until a replacement is added. For resilient read access, configure two or more secondary compute instances with read access enabled.

Change the number of secondary compute instances​

  1. On the Computes tab, click Edit on the primary compute.
  2. Under High availability, choose a new Compute configuration from the dropdown (2, 3, or 4 total compute instances).
  3. Click Save.
note

To disable high availability, set Compute type back to Single compute. This removes all secondary compute instances and your endpoint returns to a single-compute configuration.

View high availability status and roles​

The Computes tab shows every compute instance in your high availability configuration with its current role, status, and access level.

Computes tab showing one Primary compute instance with Read/Write access and three secondary compute instances with Read-only access, all ACTIVE

Column

Values

Role

Primary, Secondary

Status

Starting, Active

Access

Read/Write (primary), Read-only (secondary compute instance with access enabled), Disabled (secondary compute instance without read access)

Column

Values

Role

Primary, Secondary

Status

Starting, Active

Access

Read/Write (primary), Read-only (secondary compute instance with access enabled), Disabled (secondary compute instance without read access)

The primary compute header also shows the endpoint ID, autoscaling range, and secondary count (e.g. 8 ↔ 16 CU · 3 secondaries).

Obtain connection strings​

Click Connect on the primary compute to open the connection details dialog. The Compute dropdown lists both connection options for your high availability endpoint.

Connection details dialog showing the Compute dropdown open with Primary and Secondary RO options, and the read-only connection string displayed

Compute option

Connection string

Use for

Primary (name) ● Active

{endpoint-id}.database.{region}.databricks.com

All writes and read/write connections

Secondary (name) ● Active RO

{endpoint-id}-ro.database.{region}.databricks.com

Read offload to secondary compute instances

Compute option

Connection string

Use for

Primary (name) ● Active

{endpoint-id}.database.{region}.databricks.com

All writes and read/write connections

Secondary (name) ● Active RO

{endpoint-id}-ro.database.{region}.databricks.com

Read offload to secondary compute instances

The -ro connection string is only available when Allow access to read-only compute instances is enabled.

For complete connection string reference, see Connection strings.

Additional resources​